December 20, 2004
LOCAL UNIONS AND REGIONAL
DIRECTORS
Re: Otis GeN2 Agreement
Dear Brothers and Sisters:
Enclosed is a copy of the
settlement with Otis over the GeN2 and is self-explanatory.
As indicated on the attached
diagrams, each unit is to be shipped in multiple sections (please see diagrams
for numbered sections).
Please note that the issue of
the sheaves on the crosshead and counterweight frame has not yet been settled.
With best wishes, I remain
Fraternally yours,
James H. Chapman, Jr.
Assistant to the General
President
JHC/mrg
Encl.
OTIS / IUEC
SETTLEMENT AGREEMENT
October 28, 2004
In full and final settlement
of all issues related to Grievance IUEC-3 (excluding the dispute over the
sheaves on the crosshead and counterweight frame), filed on or about November 5, 2003 and
the dispute concerning pre-assembly of the GeN2, Otis and the IUEC agree as
follows:
1. Extended
Duty Passenger / Rear Counterweight
Car
and Counterweight Dead-end Hitch Assemblies:
- The holes for the installation of the
Counterweight Dead-end hitch assembly will be field-drilled
- The Counterweight Dead-end hitch
assembly will be field-installed before hoisting the IMBS to its final location
in the hoistway
- The Car Dead-end hitch assembly will
be removed from the IMBS and installed in the field
Car
slack rope device
- The
Car slack rope device will be field-installed after hoisting the IMBS
Governor
mounting bracket
- The holes in the outside channels for
the installation of the Governor mounting bracket will be field-drilled
- The Governor mounting bracket will be
field-installed before hoisting the IMBS to its final location in the hoistway
Governor
mounting frame:
- The governor mounting frame will be
field-installed before hoisting the IMBS to its final location in the hoistway
Rail
alignment tool:
- The holes in the outside channels for
installation of the rail alignment tools will be field-drilled
- The rail alignment tools will be
field-installed before hoisting the IMBS to its final location in the hoistway
Connection
Point Between Bedplate and Outside Channels
- Otis
will redesign the connection point between, the bedplate and the, outside
channels
- The
bedplate and outside channels will be shipped. separately and assembled in the
field
- The holes on the outside channels for
the connection between the bedplate and outside channels will be field-drilled
- All of this work will be performed
before hoisting the IMBS to its final location in the hoistway
All
field-drilled holes will be drilled before hoisting the IMBS to its final
location in the hoistway
All
field-drilled holes will be provided with 1/4 inch (or the metric equivalent)
pilot holes, except for the holes for the Counterweight dead end hitch
assembly, the Governor mounting bracket and the Rail alignment tools, for which
2 pilot holes will be provided for each component
All
bolts must be torqued to the specified values and the supervisor shall certify
that this has been done.
2. Extended
Duty Passenger / Side Counterweight
The
IMBS is shipped in two pieces that are assembled in the field before hoisting
the IMBS to its final location in the hoistway.
Car
and Counterweight Dead-end Hitch Assemblies:
- The holes for the installation of the
Counter weight Dead-end hitch assembly will be field-drilled
- The Counterweight Dead-end hitch
assembly will be field-installed before hoisting the IMBS to its final location
in the hoistway
- The Car Dead-end hitch assembly will
be removed from the IMBS and installed in the field
Car
slack rope device
- The
Car slack rope device will be field-installed after hoisting the IMBS
Governor
mounting frame:
- The holes in the outside channels for
the installation o f the Governor Mounting frame will be field-drilled
- The governor mounting frame will be field-installed
before hoisting the IMBS to its final location in the hoistway
Rail
alignment tool:
- The counterweight side Rail alignment
tool will be field-installed before hoisting the IMBS to its final location in
the hoistway
All
field-drilled holes will be drilled before hoisting the IMBS to its final
location in the hoistway
All
field-drilled holes will be provided with 1/4 inch (or the metric equivalent)
pilot holes, except for the holes for the Counterweight dead end hitch assembly
and the Governor mounting frame, for which 2 pilot holes will be provided for
each component
All
bolts must be torqued to the specified values and the supervisor will certify
that this has been done.
3. Extended Duty Hospital
/ Side Counterweight
Car
and Counterweight Dead-end Mob Assemblies:
- The holes for the installation of the
Counterweight Dead-end hitch assembly will be field-drilled
- The Counterweight Dead-end hitch
assembly will be field-installed before hoisting the IMBS to its final location
in the hoistway
- The Car Dead-end hitch assembly will
be removed from the IMBS and installed in the field
Car
slack rope device
- The
Car slack rope device will be field-installed after hoisting the IMBS
Governor
mounting frame:
- The holes in the outside channels for
the installation of the Governor mounting frame will be field-drilled
- The governor mounting frame will be
field-installed before hoisting the IMBS to its final location in the hoistway
Rail
alignment tool:
- The counterweight side Rail alignment
tool will be field-installed before hoisting the IMBS to its final location in
the hoistway
Connection
Point Between Bedplate and Outside Channels
- Otis
will redesign the connection point between the bedplate and the outside
channels
- The
bedplate and outside channels will be shipped separately and assembled in the
field
- The holes on the outside channels for
the connection between the bedplate and outside channels will be field-drilled
- All of this work will be performed
before hoisting the IMBS to its final location in the hoistway
All
field-drilled holes will be drilled before hoisting the IMBS to its final
location in the hoistway
All
field-drilled holes will be provided with 1/4 inch (or the metric equivalent)
pilot holes, except for the holes for the Counterweight dead end hitch assembly
and the Governor mounting frame, for which 2 pilot holes will be provided for
each component
All
bolts must be torqued to the specified values and the supervisor will certify
that this has been done.
In addition, for all of the
above three arrangements, the following applies:
A. Deflector
Sheaves
(i) Field
installation of counterweight deflector and car side deflector sheaves.
(ii) Those sheaves
will be installed before hoisting the IMBS to its final location in the
hoistway
B. Sheave
Keeper Plates
(i) The holes in
the sheave keeper plates will be drilled in the field
(ii) The sheave keeper plates will be bolted
into position in the field before hoisting the IMBS to its final location in
the hoistway
All
field-drilled holes will be drilled before hoisting the IMBS to its final
location in the hoistway
All
field-drilled holes will be provided with 1/4 inch (or metric equivalent) pilot
holes
All
bolts must be torqued to the specified values and the supervisor must certify
in writing that he/she has done so.
4. Otis will dismiss with prejudice Case
No. 1:03-cv-1247 (LJM) in the U.S. District Court for the Southern District of
Indiana.
5. Drawings of the models in question,
including modifications discussed herein, shall be provided to the Union and
considered a part hereof.
6. For every GeN2 installation completed
prior to the date of this Agreement, or which is in progress and beyond a point
at which the terms of this Agreement may be implemented thereon, Otis shall pay
to employees on the job four (4) team hours at the contractual wage rate plus
fringes.
7. Arbitrator Goldstein is appointed by
the parties to resolve any disputes over implementation of this agreement the
parties cannot resolve directly.
8. Otis will in good faith make every
reasonable effort to implement the terms of this Agreement by January 15, 2005.
Should the Union believe the Company is not honoring this commitment,
the Union may seek an immediate hearing before Arbitrator Goldstein.
AGREED: AGREED:
__________________________10/28/04 __________________________
Otis Elevator Company International
Union
of Elevator
Constructors
***
***
GEN2 EXTENDED DUTY
PASSENGER REAR CWT.
A

GEN2 EXTENDED DUTY
PASSENGER SIDE CWT.
B

GEN2 EXTENDED DUTY
HOSPITAL SIDE CWT.
C